GM Opens $65-Million ACDelco Parts Processing Center

General Motors this week held a grand-opening event for its new ACDelco and GM Genuine Parts processing center in Burton, MI. The 1.10-million-square-foot facility is triple the size of the facility in Burton that it’s replacing. The center will employ over 800 hourly and salaried employees — all of which support GM’s Customer Care & Aftersales business.

Construction on the new site began in June 2018, and GM shipped its first outbound delivery in June 2019. An average of 100 inbound deliveries and 55 outbound deliveries are expected each day. The facility has 84 shipping and receiving docks — up from 35 at the previous site.